Modernization of the Golina stop on RL no. 281
As part of the investment, NDI Energy modernized the Golina stop on Railway Line No. 281 in the „Design and Build” formula.
The scope of works included the demolition of existing platforms and the construction of a new single-edge platform with a length of 150 m, access to the platform, construction of a power connection to supply the new lighting and installation of platform furniture.
All the work was completed within 4 months.