Progress of work on the construction of the City Stadium in Katowice

Currently, work is being carried out on all jobsites at the City Stadium in Katowice.

On the main turf, drainage works have been completed, along with the foundation for the greenery layers, and turf drainage is being carried out on the training pitches.

A binding layer of bituminous road surface was laid in the parking lots separating the training pitches from the stadium, as well as on the road around the stadium.

The construction of foundation layers in the parking lots next to the sports hall and in the area of the media vehicles yard is also in progress.

In detail:

Around the stadium, the construction of the concrete floor on the border of the mass event area and in the corner vomitories has been completed.

Intensive work is under way on the promenade around the facility, the foundations are being successively covered with a fiber-reinforced concrete surface, and green areas are being developed in other areas.

The installation of the roofing was completed, along with the installation of the trough and drainage of the stadium roof over the three stands, the installation of the structure for the telescreens, and the installation of electric cable routes.

Preparatory work has started for the installation of fences, balustrades and seats.

Infrastructure for fans under the stands is also being built – catering boxes and sanitary rooms.

Hall

Advanced finishing works are underway in the hall building, including drywall installation, plastering and painting works.

Sanitary rooms are being equipped with concealed systems, the fan room is being equipped with air handling units, the boiler room is being equipped, the booster pump and fire systems are being equipped, and pressure tests are being carried out on the completed systems.

The erection of the ventilation system for the entertainment and sports hall has been completed

Glass façades were made for the sky boxes of the VIP zone, the sports event service rooms, and the entrance lobby of the hall.

Work is being carried out in the electrical and telecommunications parts of the project.