The Yacht Port in Górki Zachodnie will be extended

Górki Zachodnie will be even more friendly to sailors. Soon development will start, as a result of which three quays and a jetty will be extended. There will also be new platforms, a breakwater and equipment that will make visiting this venue more comfortable. The performance contract between the Directorate for the Development of the City of Gdańsk and NDI, a company based in Sopot, has just been signed.

“This is another hydraulic engineering investment that we will have the pleasure to implement, says Małgorzata Winiarek-Gajewska, President of the NDI Group. ”Recently, we have signed contracts for the development of the ports in Krynica Morska and Puck. Our company is based in Tri-City, so we are all the more pleased when we can work for the benefit of the region. As part of the investment in Górki Zachodnie, we will carry out the reconstruction of the three existing quays and the jetty, and we will take care of the delivery and assembly of new floating platforms and a floating breakwater,” adds Małgorzata Winiarek-Gajewska.

The scope of works also includes dredging the reservoir to a level of -4 meters, removal of dredging spoil from the bottom with a volume of approx. 10,700 m3 (area of approx. 14,000 m2) and the implementation of navigational markings.

The contractor is to complete the investment within 12 months. Since there are many tasks to do, it will be a busy time.

The works to be carried out on land include, among others, construction of retaining (flood protection) walls, disassembly of the existing crane and assembly of a new one at the “S” quay. A section of the sanitary sewage system will be built from the sewage collection point to the septic tank, as well as a section of the power grid, cable and telecommunication duct system.

New lighting will be installed so that the Yacht Port can be used at any time. There are also plans to build a new surface and lawns as well as place information boards.

There is even more work waiting for the contractor “on the water”. These works will include, among others, dredging works in the yacht port basin and at the Śmiała Wisła. During this work, it will also be necessary to carry out quality tests for the purity of bottom sediments and dredging spoil.

The “W”, “S”, “N” quays and the “E” jetty will also be reconstructed. Wooden platforms should also be dismantled and new floating platforms and a breakwater built.

The NDI Group must take care of the quay equipment: mooring bollards, access ladders, fendering, lifebuoy stands, lighting pedestals equipped with electrical sockets and water valves. There will also be rescue equipment and a ramp for disabled people.

The investor is the Directorate for the Development of the City of Gdańsk. Biuro Projektów Budownictwa Morskiego Projmors Sp. z o. o. is responsible for the project. The cost of the works is over PLN 18.5 million.