Construction of the A1 motorway in the PPP formula

Construction of the A1 motorway in the PPP formula

PPP - Construction of the A1 Motorway

In consortium with Skanska SA we built the northern section of A1 motorway with a length of 152 km. It was project of a strategic significance to the national transport grid.

We were also involved in the project in the capacity of a joint investor via our subsidiary holding an equity interest in the concessionaire – Gdańsk Transport Company S.A. (GTC SA).

A flight over the construction site of the A1 Motorway on the section Gdańsk-Toruń

Public Private Partnership – A1 Motorway

The project is pursued under the public-private formula with the government on the one hand and the private partner (GTC S.A.) on the other hand.

Gdańsk Transport Company S.A. (GTC S.A.) was the latter accountable for comprehensive implementation of the project consisting in the designing, financing, construction, operation, and maintenance of the motorway.

NDI has made use of its years’ long experience in development to commit itself especially to the structuring and financing of the project.

The construction of the152 km long concession-based section of the A1 Motorway was split into two phases:

icon

Phase I

The signing with the government, in the year 2004, of the agreement to build the first stage in the investment, i.e. the 90-km long motorway section from Rusocin to Nowe Marzy. The contract value amounted to EUR529 MM.

icon

Phase II

The signing with the government, in the year 2008, of the agreement to build the second stage in the investment, i.e. the 62-km long section from Nowe Marzy toToruń. The contract value amounted to EUR730 MM.

Phase I in number


project value

529 mln €


length of the motorway section

90 km


of soil moved

23 mln m³


86

bridge structures

6

interchanges

6

toll plazas

2

maintenance areas (OUAs)

3

double service areas (MOPs)

4,5

4.5 months before the handover date

123

thousand cubic meters of concrete

1600

thousand tonnes of the bitumen mix

Phase II in number


project value

730 mln €


the length of the motorway section

62 km


of soil moved

10 mln m³


51

new bridges, including two large bridges over the Vistula River

5

interchanges

6

toll plazas

1

maintenance area OUA

4

double service areas MOPs

15

modernized overbridges

225

thousand cubic meters of concrete

1300

thousand tonnes of the bitumen mix

Name of location:

The bridge near Grudziądz

87-134 Rozgarty